Alignment
Alignment construction update
TUNNELLING PROGRESS On Wednesday 24 April, tunnel boring machine (TBM), Joyce, broke through at the eastern portal. Transcity…
Read More.Alignment construction update
TUNNELLING PROGRESS Tunnelling on Legacy Way continues, with the second tunnel boring machine (TBM), Joyce, approaching the eastern…
Read More.Alignment construction update
TUNNELLING PROGRESS Tunnelling on Legacy Way continues, with the second tunnel boring machine (TBM), Joyce, averaging 30 metres…
Read More.Alignment construction update
TUNNELLING PROGRESS Tunnelling on Legacy Way continues with the first tunnel boring machine (TBM), Annabell, averaging 17 metres…
Read More.Alignment construction update
TUNNELLING PROGRESS Tunnel boring machines Tunnelling on Legacy Way continues with the first tunnel boring machine (TBM), Annabell,…
Read More.Alignment construction update
Tunnelling progress Tunnel boring machines Tunnelling on Legacy Way continues with the first tunnel boring machine (TBM), Annabell,…
Read More.Track the TBMs progress on our alignment map
Track the TBMs progress on our alignment map
Read More.Alignment construction update
TUNNELLING PROGRESS Tunnel boring machines Tunnelling on Legacy Way continues with the first tunnel boring machine (TBM), Annabell,…
Read More.Alignment construction update
TUNNELLING PROGRESS Tunnelling on Legacy Way continues with the first tunnel boring machine (TBM), Annabell, completing excavation between…
Read More.Alignment update
Tunnelling Underway Tunnelling on Legacy Way has started with the launch of the first tunnel boring machine (TBM),…
Read More.